Bloor Homes started work on site in May 2015 to construct 59 new homes for Suffolk Housing Society.

The delivery of the units has been split into five phases, with the first phase completing in October 2015 and the final phase due for completion in June 2017.

The 59 units comprise of 42 Affordable Rented units and 17 Shared Ownership units.

Key facts:

  • Project Value: £6 million
  • Grant Received: Nil
  • Start on site: May 2015
  • Anticipated Completion: December 2017
  • Architect: Bloor Homes
  • Contractor: Bloor Homes
  • Employers Agent: Oxbury & Co
  • Tenure: Mixture of Affordable rent and shared ownership
Mill Heath Martlesham
Mill Heath Martlesham